Kitchen extension in Trowell, Nottingham
A 3m by 6m kitchen extension on a semi, built under permitted development in about 8 weeks. The customer did their own plasterboard and plastering to save money.




A single-storey rear extension on a semi-detached house, for a new, bigger kitchen. It comes 3m out from the house and is about 6m wide, with a tiled pitched roof and two Velux windows letting daylight into the middle of the room. It was all done under permitted development, so no planning application.
How did the customer save money?
We took the inside up to the stage just before plasterboard, and the customer is doing the plasterboard and plastering themselves. We agreed that with them before we started, and it’s a big part of why the job came in at about £35,000 + £7,000 VAT = £42,000, at the lower end for an extension this size.
Were there any challenges?
The garden slopes, so the ground drops away from the house. That meant building quite a few extra courses of blue engineering brick at the bottom of the walls to get up to floor level. To make that base strong enough, we filled the cavity in those courses with concrete, so it works as part of the footing rather than just a hollow wall. You can see the blue brick band running round the bottom in the photos.
Other than the slope, it was a smooth, straightforward job.
How the build went
- Footings. Dug and poured, allowing for the slope of the garden.
- Engineering brick base. Extra courses of blue engineering brick to make up the slope, with the cavity filled with concrete for strength.
- Walls and roof. Red brick walls, then a tiled pitched roof with two Veluxes, and the window and side door fitted.
- Inside. Opened up into the house and taken up to just before plasterboard, ready for the customer to board and plaster.
Read all reviews →“They were easy to work with. Even when some plans got changed last minute. They did a great job on the extention.”
Other extension case studies
Thinking about your own extension?
Get a free, no-obligation quote. We don’t take a deposit, and the final payment is only due when the job is finished.